Below is a summary of activities completed during the previous period. Pouring concrete parquet flooring main corridor: This activity is completed at 85% during this week. Pouring concrete parquet flooring, block 5 (cafeteria) : This activity is not completed during this week. Electrical installation of classroom ceilings: This activity is not completed during this week.… Continue reading Week 66 – Sept 18-25, 2024 – Building the Jolley School, Timo Haiti
Month: September 2024
Week 65 (Sept 11-Sept 18, 2024) – Building the Jolley School, Timo Haiti
Update!!! (100%)|Pouring concrete parquet flooring, block 4 (Classrooms 4-6), 100%. Steel reinforcement plant boat, 100%. Formwork plant boat, 100%. Pouring concrete plant boat, 100%. Laying bloc plant boat, 50%. Steel reinforcement corridor between block 3 (Classrooms 1-3) and block 4(Classrooms 4-6), 50%. Floating, block 5(Cafeteria), 100%. Main facade preparation,100%. Bench preparation, 20%. Saddling socket,90%
Week 64 (Sept 4-Sept 11, 2024) – Building the Jolley School, Timo Haiti
Update on progress: pouring concrete parquet flooring,block 4 ( Classrooms 4-6); This activity is completed at 75% during this week. Paint work block 4(Classrooms 4-6) : This activity is completed at 30 % during this week. plant boat excavation : This activity is completed during this week, 100%. Backfilling corridor between block 3(Classrooms 1-3) and… Continue reading Week 64 (Sept 4-Sept 11, 2024) – Building the Jolley School, Timo Haiti
Primer and Paint!!!
It’s starting to look like a school!!!
Transforming Rural Haiti’s Primary Education: Best Practices for Success
Haiti’s primary education system faces numerous challenges, but there’s hope on the horizon. We’ve identified several best practices that are making a real difference in Haitian classrooms. These innovative approaches are helping to overcome obstacles and improve learning outcomes for young students across the country. From implementing mother-tongue instruction to fostering community involvement, Haiti’s educators… Continue reading Transforming Rural Haiti’s Primary Education: Best Practices for Success
Week 63 (Aug 28-Sept 2, 2024)
Recap of the week: Installation Windows, block 1 (Administration), 100%. Installation Windows, block 2 (Library / Computer), 40%. Installation Windows, block 3 (Classromms 1-3), 100%. Installation Windows, block 4 (Classromms 4-6), 60%. Floating, block 4(Classrooms 4-6), 100%. Floating, block 5(Cafeteria), 85%. Floating window toilet,80%. Main corridor préparation (80%). starting paint work (application of base or… Continue reading Week 63 (Aug 28-Sept 2, 2024)