Weed 68: (Oct 3- Oct 10, 2024) Building the Jolley School in Timo

Recap: Steel reinforcement for concrete floor between Block 5 (Kitchen/Cafeteria), 100%. Electrical work Block 5 hallway 3 & 4, 50%. Pouring concrete parquet flooring, Block 5 (Kitchen/Cafeteria), 60%. Application of paint on walls, 50% Classroom doors installation, 100% Manufacturing student benches/desks, 45% Windows installation Our operations are currently at the following stages: Wall finishing; Building… Continue reading Weed 68: (Oct 3- Oct 10, 2024) Building the Jolley School in Timo

Week 67 – (Sept 26- Oct 3, 2024) Building the Jolley School in Timo

Update!!! Steel reinforcement hallway between Block (Classrooms 1-3) and Block 4(Classrooms 4-6), 100%. Electrical installation hallway between Block 3(Classrooms 1-3) and block 4(Classrooms 4-6), 100%. Pouring concrete parquet flooring main hallway, 100%. Electrical work classroom ceilings, 100%. Pouring concrete parquet flooring, Block 5 (Kitchen/Cafeteria), 80%. Making school bench, 45%. Laying concrete blocks for planter boxes… Continue reading Week 67 – (Sept 26- Oct 3, 2024) Building the Jolley School in Timo