Week 62 (Aug 21-Aug 28) – Building of the Jolley School
Construction of Jolley School, School
'}}

Update:

  • Steel reinforcement parquet floor, block 4 (Classrooms 4-6),100%.
  • Electrical flooring, block 4(Classrooms 4-6), 100%.
  • concrete pouring parquet floor, block 3(Classrooms 1-3), 100%.
  • Floating, block 3(Classrooms 1-3), 100%.
  • Concrete pouring parquet floor, block 3(Classrooms 1-3), 100%.
  • Plug sealing, block 4(Classrooms 4-6) ,100%.
  • Purchase and transport of 300 bags of cement (100%).
  • Facade préparation (100%).