Week 63 (Aug 28-Sept 2, 2024)

Recap of the week: Installation Windows, block 1 (Administration), 100%. Installation Windows, block 2 (Library / Computer), 40%. Installation Windows, block 3 (Classromms 1-3), 100%. Installation Windows, block 4 (Classromms 4-6), 60%. Floating, block 4(Classrooms 4-6), 100%. Floating, block 5(Cafeteria), 85%. Floating window toilet,80%. Main corridor préparation (80%). starting paint work (application of base or… Continue reading Week 63 (Aug 28-Sept 2, 2024)