AMAZING PROGRESS!!! CHECK OUT THE JOLLEY BUILDING
Isn’t this incredible!!! It looks like a real live school!!!
Weed 68: (Oct 3- Oct 10, 2024) Building the Jolley School in Timo
Recap: Steel reinforcement for concrete floor between Block 5 (Kitchen/Cafeteria), 100%. Electrical work Block 5 hallway 3 & 4, 50%. Pouring concrete parquet flooring, Block 5 (Kitchen/Cafeteria), 60%. Application of paint on walls, 50% Classroom doors installation, 100% Manufacturing student benches/desks, 45% Windows installation Our operations are currently at the following stages: Wall finishing; Building… Continue reading Weed 68: (Oct 3- Oct 10, 2024) Building the Jolley School in Timo
Week 67 – (Sept 26- Oct 3, 2024) Building the Jolley School in Timo
Update!!! Steel reinforcement hallway between Block (Classrooms 1-3) and Block 4(Classrooms 4-6), 100%. Electrical installation hallway between Block 3(Classrooms 1-3) and block 4(Classrooms 4-6), 100%. Pouring concrete parquet flooring main hallway, 100%. Electrical work classroom ceilings, 100%. Pouring concrete parquet flooring, Block 5 (Kitchen/Cafeteria), 80%. Making school bench, 45%. Laying concrete blocks for planter boxes… Continue reading Week 67 – (Sept 26- Oct 3, 2024) Building the Jolley School in Timo
Week 66 – Sept 18-25, 2024 – Building the Jolley School, Timo Haiti
Below is a summary of activities completed during the previous period. Pouring concrete parquet flooring main corridor: This activity is completed at 85% during this week. Pouring concrete parquet flooring, block 5 (cafeteria) : This activity is not completed during this week. Electrical installation of classroom ceilings: This activity is not completed during this week.… Continue reading Week 66 – Sept 18-25, 2024 – Building the Jolley School, Timo Haiti
Week 65 (Sept 11-Sept 18, 2024) – Building the Jolley School, Timo Haiti
Update!!! (100%)|Pouring concrete parquet flooring, block 4 (Classrooms 4-6), 100%. Steel reinforcement plant boat, 100%. Formwork plant boat, 100%. Pouring concrete plant boat, 100%. Laying bloc plant boat, 50%. Steel reinforcement corridor between block 3 (Classrooms 1-3) and block 4(Classrooms 4-6), 50%. Floating, block 5(Cafeteria), 100%. Main facade preparation,100%. Bench preparation, 20%. Saddling socket,90%
Week 64 (Sept 4-Sept 11, 2024) – Building the Jolley School, Timo Haiti
Update on progress: pouring concrete parquet flooring,block 4 ( Classrooms 4-6); This activity is completed at 75% during this week. Paint work block 4(Classrooms 4-6) : This activity is completed at 30 % during this week. plant boat excavation : This activity is completed during this week, 100%. Backfilling corridor between block 3(Classrooms 1-3) and… Continue reading Week 64 (Sept 4-Sept 11, 2024) – Building the Jolley School, Timo Haiti
Primer and Paint!!!
It’s starting to look like a school!!!
Week 62 (Aug 21-Aug 28) – Building of the Jolley School
Update: Steel reinforcement parquet floor, block 4 (Classrooms 4-6),100%. Electrical flooring, block 4(Classrooms 4-6), 100%. concrete pouring parquet floor, block 3(Classrooms 1-3), 100%. Floating, block 3(Classrooms 1-3), 100%. Concrete pouring parquet floor, block 3(Classrooms 1-3), 100%. Plug sealing, block 4(Classrooms 4-6) ,100%. Purchase and transport of 300 bags of cement (100%). Facade préparation (100%).
Week 61 (Aug 14-Aug 21, 2024) – Building of the Jolley School
Review of activities from the previous period : Transportation of doors, 19 units 100%. Transportation of windows, 100%. 21 units Steel reinforcement parquet floor, block 3 (Classrooms 1-3) ,100%. Electrical flooring, block 3(Classrooms 1-3), 100%. Concrete pouring parquet floor, block 3(Classrooms 1-3), 70%. Plug sealing, block 1(Administration) ,100%. Plug sealing, block 2(Library / Computer) ,100%.… Continue reading Week 61 (Aug 14-Aug 21, 2024) – Building of the Jolley School