Week 37: (Feb 29-Mar 7, 2024)

Week 37: (Feb 29-Mar 7, 2024) School completion update: Based on the Calendar, we are in Week #37 of the school construction project, which is expected to conclude by Week #38. The project has progressed each week, thanks to the leadership of the Haitian contractor, Ing. Francillon, who adjusted strategies multiple times to address project… Continue reading Week 37: (Feb 29-Mar 7, 2024)

Week 45 (April 24-March 1, 2024) — Building the Jolley School, Timo Haiti

Week 45 (April 24-March 1, 2024) Interesting fact: Skilled workers are not from Timo but they have temporary housing in the Timo community during the construction project. Skilled workers include carpenters who build formwork; steel workers who build steel reinforcement; masons who pour concrete. Daily laborers, Timo natives, assist skill workers in various ways, including… Continue reading Week 45 (April 24-March 1, 2024) — Building the Jolley School, Timo Haiti

Week 36 (Feb 22-29, 2024)

Week 36 (Feb 22-29, 2024) Review of work for the week: -Transported 4200 lbs of rebar from Leogane to Tavet, 100% of goal complete. -Transported 200 cement bags from Petit Goâve to Tavet, 80% complete. -Steel reinforcement for intermediary chain beam, Block 4 (Classrooms), 0% complete. -Formwork for intermediate chain beam, Block 4 (Classrooms), 0%… Continue reading Week 36 (Feb 22-29, 2024)

Week 35 – (Feb 9-15, 2024) – Building of the Jolley School

Week 35 – (Feb 9-15, 2024) RECAP: The project has consistently advanced each week, thanks to the leadership of the wise and experienced Haitian contractor. He has adjusted strategies multiple times to address project requirements and resolve emerging challenges. Nevertheless, the project has encountered significant delays due to persistent obstacles, including the prevailing security concerns… Continue reading Week 35 – (Feb 9-15, 2024) – Building of the Jolley School