Recap:
- Steel reinforcement for concrete floor between Block 5 (Kitchen/Cafeteria), 100%.
- Electrical work Block 5 hallway 3 & 4, 50%.
- Pouring concrete parquet flooring, Block 5 (Kitchen/Cafeteria), 60%.
- Application of paint on walls, 50%
- Classroom doors installation, 100%
- Manufacturing student benches/desks, 45%
- Windows installation
Our operations are currently at the following stages: Wall finishing; Building roofing; Door and window installation; Electrical installation; Plumbing and fixtures; Painting; and Furnishing.