Week 41 (March 28-April 4, 2024) — Building the Jolley School, Timo Haiti
Construction of Jolley School, School
'}}

Week 41 (March 28-April 4, 2024)

Progress:
-We are still at STEP 4 (Step 4 Vertical Wall Erection: Concrete Block and Masonry) of the Calendar of Activities agreed upon on May 18, 2023.
-Below is a summary of activities completed during the previous period.
-Steel columns installation, Block 5 (Kitchen/Cafeteria), 100% complete.
-Laying cement blocks on floor beams for the partition walls, 100% complete
-Laying cement blocks, Block 5, 80% complete
-Steel rebar for intermediate chain beam, Block 5, 100% complete
-Formwork for intermediate chain beam, Block 5, 100% complete
-Concrete pouring on intermediate chain beam, Block 5, 100 % complete
-Formwork for doors and windows, Block 4 (Classrooms 4-6), 100% complete​.