Week 67 – (Sept 26- Oct 3, 2024) Building the Jolley School in Timo
October 3, 20241 min read

Update!!!
- Steel reinforcement hallway between Block (Classrooms 1-3) and Block 4(Classrooms 4-6), 100%.
- Electrical installation hallway between Block 3(Classrooms 1-3) and block 4(Classrooms 4-6), 100%.
- Pouring concrete parquet flooring main hallway, 100%.
- Electrical work classroom ceilings, 100%.
- Pouring concrete parquet flooring, Block 5 (Kitchen/Cafeteria), 80%.
- Making school bench, 45%.
- Laying concrete blocks for planter boxes in the main hallway, 100%.
- plastering planter boxes, 50%.
Our operations are currently at the following stages: Wall finishing; Building roofing; Door and window installation; Electrical installation; Plumbing and fixtures; Painting; and Furnishing.
Six trades are currently hard at work simultaneously: Carpenters for door installation, manufacturing tables for computers, cafeteria tables, and shelves for the library, as well as shelves in the kitchen storage. Metalworkers are installing windows; masons are working on concrete flooring for the classrooms and cafeteria; electricians are finalizing electrical installations; and painters are applying the final coats of paint on the interior walls and the initial coat on the exterior walls.