Week 35 – (Feb 9-15, 2024) – Building of the Jolley School
Construction of Jolley School, School
'}}

Week 35 - (Feb 9-15, 2024)

RECAP:
The project has consistently advanced each week, thanks to the leadership of the wise and experienced Haitian contractor. He has adjusted strategies multiple times to address project requirements and resolve emerging challenges. Nevertheless, the project has encountered significant delays due to persistent obstacles, including the prevailing security concerns across Haiti, intermittent interruptions caused by adverse weather conditions, the remote location of the project site, requests from workers for wage adjustments to transport cement blocks, and negotiations with a local resident regarding compensation for the use of the pulley system on her property. In two weeks’ time (by March 7), the Haitian contractor will provide a schedule addendum outlining his revised expectations for the completion of the school construction.
Explanation of pictures and progress:
-Transported 2325 cement blocks (size 15 cm) from Petit Goâve to Tavet, completed 175% of the goal
-Transported 6600 lbs of rebar from Leogane to Tavet, 600% of the goal complete
-Steel reinforcement for intermediary chain beam, Block 1 (Administration Offices), 100% complete
-Formwork for intermediate chain beam, Block 1 (Administration Offices), 100% complete
-Concrete pouring for intermediary chain beam, Block 1 (Administration Offices), 100% complete
- Steel reinforcement for intermediary chain beam, Block 2 (Library/Computer Room), 100% complete
-Concrete pouring for intermediary chain beam, Block 2 (Library/Computer Room), 100% complete.
-Backfilling and interior compaction, Block 5 (Kitchen/Cafeteria)
-Laying 15cm Block wall panel, Block 3 (Classrooms)