Construction of Jolley School, School
'}}

Week 39 (March 14-21, 2024)

Most of the programming for this week [see activities a) through e)] had not been carried out. Skilled workers who are not from the Timo area had a rare opportunity to go visit their families. Given the current situation in the country, these skilled workers got stuck at home and couldn’t travel back to the construction site on the scheduled date; therefore, the resumption of work is set for March 21, 2024.
Progress made:
-Laying cement blocks, Block 4 (Classrooms 4-6), 85% complete