Week 44 (April 17-24, 2024) Building the Jolley School, Timo Haiti
Construction of Jolley School, School
'}}
Week 44 (April 17-24, 2024)
Below is a summary of activities completed during the previous period.
-Laying cement blocks for partition walls, Block 5 (Kitchen/Cafeteria), 100% complete
-Formwork for doors and windows, Block 5 (Kitchen/Cafeteria), 100% complete
-Concrete pouring for doors and windows, Block 5 (Kitchen/Cafeteria), 100% complete.
-Concrete pouring for front door threshold, Block 1 (Administration) & Block 2 (Library/Computer Room), 100% complete
-Formwork doors, Block 1 (Administration) & Block 2 (Library/Computer Room), 100% complete
-Concrete pouring for doors, Block 1 (Administration) & Block 2 (Library/Computer Room), 100% complete
Percentage général des travaux exécutés |Overall percentage of work completed
52.00%
Previous period: 50%