1) Steel reinforcement for top chain beam, Block 1 (Administration), 100% complete
2) Steel reinforcement for top chain beam, Block 2 (Library /Computer Room), 75% complete
3) Formwork for top chain beam, Block 1(Administration), 0% complete
4) Steel roof anchoring installation, Block 1 (Administration), 0% complete
5) Steel roof anchoring installation, Block 2 (Library/ Computer Room) (0%) complete
6) Concrete pouring for lower chain beam, office partition walls, Block 1 (Administration), 100% complete