Week 49 (May 22-29, 2024) – Building of Jolley school Timo, Haiti
School
'}}

WEEK 49 (May 22-29, 2024)

Below is a summary of activities completed during the previous period:
1) Steel reinforcement for top chain beam, Block 3 ; activity is completed at 70% during this week.
2) Formwork for top chain beam, Block 3 (Classrooms 1-3) : this activity is completed at 20 % during this week .
3) Steel reinforcement for top chain beam, Block 1 (Administration), ; this activity is completed during this week (100%) .
4) Formwork for top chain beam, Block 1 (Administration), (100%) : this activity is completed during this week,(100% ).
5) Pouring concrete for top chain beam, Block 1 (Administration), (100%): this activity is completed during this week,(100% ).
6) Steel reinforcement for top chain beam, Block 2(Library/Computer), (100%): this activity is completed during this week at 100%.
7) Formwork for top chain beam, Block 2 (Library / Computer), (100%): this activity is completed during this week at 100%
😎 Pouring concrete for top chain beam, Block 2 (Library / Computer), (100%): this activity is completed during this week at 100%
9) Steel reinforcement for top chain beam partition for block 1 (Administration),: this activity is completed during this week at 100%
10) Formwork for top chain beam partition for block 1(Administration), this activity is completed during this week at 100%
11) Pouring concrete for top chain beam partition for block 1 (Administration), this activity is completed during this week,(100%) .
12) Steel reinforcement for top chain beam, Block 4 (Classrooms 4-6), (5%): this activity is completed during this week at 100%
13) Formwork fortop chain beam, Block (Classrooms 4-6), (5%): activity is completed at 5% during this week.
14) Steel structure for roofing, Block 1( Administration),(5%): this activity is completed at 5% during this week.
15) Steel structure for roofing , Block 2(Library/ computer),(5%) : this activity is completed at 5% during this week.