Week 58 (July 24-July 31, 2024) – Building of the Jolley School
Construction of Jolley School, School
'}}

Update:

  • Aluzinc sheet metal installation main ridge, 70%.
  • Aluzinc sheet metal installation, block 1(Administration), 100%.
  • Aluzinc sheet metal installation, block 2(Library / Computer), 70%.
  • Aluzinc sheet metal installation, block 3(Classrooms 1-3), 100%.
  • Aluzinc sheet metal installation, block 4(Classrooms 4-6), 70%.
  • Floating, block 1 (Administration), 90%.
  • Floating, block 2 (Library / Computer), 80%.
  • Plastering chain beam, block 3 (Classrooms 1-3) ,50%.
  • Floating, block 3 (Classrooms 1-3), 50%.
  • Steel frame for parquet flooring, block 1 (Administration), 0%.
  • Installation of electrical piping 1,0%.
  • Steel frame for parquet flooring, block 2 (Library / Computer), 0%.
  • Installation of electrical piping 1 ,0%.
  • Demolition of latrine toilets,100%.
  • Steel structure for roofing, block 5(Cafeteria), 50%.