Projects
Education
Medical
Water
Nutrition
Dental
Multi Purpose Community Center
About
Why Haiti
HHI Leadership
HHI Leadership – USA
HHI Leadership – Haiti
Sustainable Development
Haiti Health News
Documents
Partners
Donate
Volunteer
Blog
Contact
Projects
Education
Medical
Water
Nutrition
Dental
Multi Purpose Community Center
About
Why Haiti
HHI Leadership
HHI Leadership – USA
HHI Leadership – Haiti
Sustainable Development
Haiti Health News
Documents
Partners
Donate
Volunteer
Blog
Contact
DONATE NOW
Week 58 (July 24-July 31, 2024) – Building of the Jolley School
Construction of Jolley School, School
Update:
Aluzinc sheet metal installation main ridge, 70%.
Aluzinc sheet metal installation, block 1(Administration), 100%.
Aluzinc sheet metal installation, block 2(Library / Computer), 70%.
Aluzinc sheet metal installation, block 3(Classrooms 1-3), 100%.
Aluzinc sheet metal installation, block 4(Classrooms 4-6), 70%.
Floating, block 1 (Administration), 90%.
Floating, block 2 (Library / Computer), 80%.
Plastering chain beam, block 3 (Classrooms 1-3) ,50%.
Floating, block 3 (Classrooms 1-3), 50%.
Steel frame for parquet flooring, block 1 (Administration), 0%.
Installation of electrical piping 1,0%.
Steel frame for parquet flooring, block 2 (Library / Computer), 0%.
Installation of electrical piping 1 ,0%.
Demolition of latrine toilets,100%.
Steel structure for roofing, block 5(Cafeteria), 50%.