Week 60 (Aug 7-Aug 14) – Building of the Jolley School
August 14, 20241 min read

Recap:
- concrete pouring parquet floor, block 1(Administration), 100%.
- concrete pouring parquet floor, block 2(Library / Computer), 100%.
- Aluzinc sheet metal installation, block 5,100 %.
- Floating, block 3 (Classrooms 1-3), 100 %.
- Floating, block 4 (Classrooms 4-6), 100%.
- Aluzinc sheet metal installation, main corridor, blocks 3(Classrooms 1-3) and 4(Classrooms 4-6), 100%.
- Transportation of windows for blocks 1
(Administration) and 2 (Library / Computer) ,100%. - Transportation of doors for blocks 1 (Administration) and 2 (Library / Computer) ,100%.