Review of activities from the previous period :
- Transportation of doors, 19 units 100%.
- Transportation of windows, 100%. 21 units
- Steel reinforcement parquet floor, block 3 (Classrooms 1-3) ,100%.
- Electrical flooring, block 3(Classrooms 1-3), 100%.
- Concrete pouring parquet floor, block 3(Classrooms 1-3), 70%.
- Plug sealing, block 1(Administration) ,100%.
- Plug sealing, block 2(Library / Computer) ,100%.
- Plug sealing, block 3(Classroms 1-3) ,100%.