Week 62 (Aug 21-Aug 28) – Building of the Jolley School
August 28, 20241 min read

Update:
- Steel reinforcement parquet floor, block 4 (Classrooms 4-6),100%.
- Electrical flooring, block 4(Classrooms 4-6), 100%.
- concrete pouring parquet floor, block 3(Classrooms 1-3), 100%.
- Floating, block 3(Classrooms 1-3), 100%.
- Concrete pouring parquet floor, block 3(Classrooms 1-3), 100%.
- Plug sealing, block 4(Classrooms 4-6) ,100%.
- Purchase and transport of 300 bags of cement (100%).
- Facade préparation (100%).