Week 63 (Aug 28-Sept 2, 2024)
Uncategorized
'}}

Recap of the week:

  • Installation Windows, block 1 (Administration), 100%.
  • Installation Windows, block 2 (Library / Computer), 40%.
  • Installation Windows, block 3 (Classromms 1-3), 100%.
  • Installation Windows, block 4 (Classromms 4-6), 60%.
  • Floating, block 4(Classrooms 4-6), 100%.
  • Floating, block 5(Cafeteria), 85%.
  • Floating window toilet,80%.
  • Main corridor préparation (80%).
  • starting paint work (application of base or top coat), 5%. MASONRY WORK ON THE SITE IS SLOWING DOWN DUE TO A BREAKDOWN