Week 63 (Aug 28-Sept 2, 2024)
September 2, 20241 min read

Recap of the week:
- Installation Windows, block 1 (Administration), 100%.
- Installation Windows, block 2 (Library / Computer), 40%.
- Installation Windows, block 3 (Classromms 1-3), 100%.
- Installation Windows, block 4 (Classromms 4-6), 60%.
- Floating, block 4(Classrooms 4-6), 100%.
- Floating, block 5(Cafeteria), 85%.
- Floating window toilet,80%.
- Main corridor préparation (80%).
- starting paint work (application of base or top coat), 5%. MASONRY WORK ON THE SITE IS SLOWING DOWN DUE TO A BREAKDOWN