Week 65 (Sept 11-Sept 18, 2024) – Building the Jolley School, Timo Haiti
September 18, 20241 min read

Update!!!
- (100%)|Pouring concrete parquet flooring, block 4 (Classrooms 4-6), 100%.
- Steel reinforcement plant boat, 100%.
- Formwork plant boat, 100%.
- Pouring concrete plant boat, 100%.
- Laying bloc plant boat, 50%.
- Steel reinforcement corridor between block 3 (Classrooms 1-3) and block 4(Classrooms 4-6), 50%.
- Floating, block 5(Cafeteria), 100%.
- Main facade preparation,100%.
- Bench preparation, 20%.
- Saddling socket,90%