Projects
Education
Medical
Water
Nutrition
Dental
Multi Purpose Community Center
About
Why Haiti
HHI Leadership
HHI Leadership – USA
HHI Leadership – Haiti
Sustainable Development
Haiti Health News
Documents
Partners
Donate
Volunteer
Blog
Contact
Projects
Education
Medical
Water
Nutrition
Dental
Multi Purpose Community Center
About
Why Haiti
HHI Leadership
HHI Leadership – USA
HHI Leadership – Haiti
Sustainable Development
Haiti Health News
Documents
Partners
Donate
Volunteer
Blog
Contact
DONATE NOW
Week 66 – Sept 18-25, 2024 – Building the Jolley School, Timo Haiti
Construction of Jolley School, School
Below is a summary of activities completed during the previous period
.
Pouring concrete parquet flooring main corridor:
This activity is completed at 85% during this week.
Pouring concrete parquet flooring, block 5 (cafeteria) :
This activity is not completed during this week.
Electrical installation of classroom ceilings:
This activity is not completed during this week.
concrete preparation for outdoor sidewalk:
This activity is completed during this week.
Steel reinforcement corridor between block 3(Classrooms 1-3) and block 4(Classrooms 4-6) :
This activity is completed at 100% during this week.
Electrical pipe installation corridor
between block 3(Classrooms 1-3) and block 4(Classrooms 4-6)
:
This activity is completed at 100% during this week.
Roof repair (toilet)
:
This activity is completed at 98% during this week.
Bench preparation :
This activity is completed at 35% during this week.
Laying bloc plant boat:
This activity is completed at 100% during this week.
plastering plant boat
:. This activity is completed at 50% during this week.